CURRENT - Tanami Expansion 2 Project

Location: Tanami

Expected Completion: August 2025

Client: Newmont

Underground Construction

Shaft Collar & Civils

Location: Prominent Hill

Completed: 2022

Client: Oz Minerals

Refrigeration Plant & Underground Fans

Location: Prominent Hill

Expected Completion: April 2023

Client: BHP

Values-01.png

Project:

T3 Cleaner Circuit

Location: Cadia

Completed: 2017

Client: Monadelphous

VR11 & VR51 Western Ventilation Fans

Location: Cadia

Completed: May 23

Client: TLT-Turbo

Coarse Flotation Project

Location: Carrapateena

Expected Completion: June 24

Client: BHP

Mining Support Services

Location: Savage River

Expected Completion: Ongoing

Client: Grange Resources

Pump Chamber & Misc

Location: Lake Cowal

Expected Completion: July 24

Client: Evolution

Cadia Expansion Project Stages 1, 2 & 3

Location: Cadia

Completed: June 2022

Client: Newcrest Mining

CURRENT - Crusher 2

Location: Carrapateena

Expected Completion: October 2023

Client: Oz Minerals

Values-8-1M.png

Underground Crusher

Location: Carrapateena

Duration: 9 months

Completed: 2020

Client: Oz Minerals

Values-02.png

Project: Con 1, Con 2, Reclaim

Location: Cadia

Completed: 2016

Client: Newcrest Mining

Values-7-5M.png

Molybdenum Plant

Location: Cadia

Completion: November 2021

Client: Worley

Underground Crusher

Location: North Parkes

Completed: 2021

Client: CMOC

Jameson Cell

Location: Prominent Hill

Expected Completion: July 24

Client: BHP

Chiller Upgrade

Location: Cadia

Expected Completion: June 24

Client: Newmont

Diesel Fuel Upgrade

Location: Cadia

Expected Completion: June 24

Client: Newmont